ADU permit process in Campbell, California
Last verified August 29, 2026
Prepared by GetYourPermit editorial teamReport an error
This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.
Where to apply
- Department
- Building Inspection Division
- Permit portal
- City Online Portal System
Step by step
- 1
Select ADU route and confirm conditional Planning requirements
Review City Bulletin and correct application guide For new detached/attached ADU use City new-residential guide; confirm conversion planning condition Applicable City permit package
- 2
Submit complete electronic Building Permit application
Create MGO account Upload complete electronic package MGO Building Permit submission
- 3
City checks upload adequacy
Correct missing, inadequate, mislabeled or improperly formatted material if rejected Accepted application or MGO rejection notice
- 4
City plan review
Respond to City plan-check comments Plan-check comments or approval-ready package
- 5
Submit response letter and corrections
Prepare itemized response to each City plan-check comment Upload subsequent submittal Corrected resubmittal
- 6
Satisfy known JADU issuance condition
For JADU, record deed restriction before Building Permit issuance Building Permit issuance stage
- 7
Schedule construction inspections
Request inspection through MGO or phone Provide AM/PM preference if desired Field combination inspection
What you need to submit
- Electronic ADU/JADU application materials and construction plans
- Applicant response letter to plan-check comments
- Recorded JADU deed restriction
Project-specific next step
Build your Campbell permit report
Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.
Sources for this guide
Additional city reference pages
The City current FY 2026-27 master schedule lists building-valuation formulas, plan check, ADU post-entitlement planning fees, and the ADU park in-lieu rule.
Accessed August 28, 2026
- CityFees
The City live Fees page identifies FY 2026-27 and links directly to the current FY 2027 Master Fee Schedule.
Accessed August 28, 2026
The City bulletin states an ADU/JADU needs a complete Building Division permit application and does not require a land-use entitlement.
Accessed August 28, 2026