This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.

Where to apply

Step by step

  1. 1

    Prepare ADU application and digital plans

    Complete City ADU Application Prepare City-required digital plan set Use Accela process for ADU application Submitted ADU application

  2. 2

    City plan check of submitted ADU plans

    Provide any additional information City requires after review Plan-check review

  3. 3

    Obtain Building & Safety permit and approval

    Meet City conditions communicated through the permit process Building Permit and approval

What you need to submit

  • City ADU Application
  • Digital ADU plan set

Pre-approved ADU plans

Use Lancaster’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.

View pre-approved plans

Project-specific next step

Build your Lancaster permit report

Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.

Start my permit report

Sources for this guide

Additional city reference pages

  • The official Building and Safety page identifies and directly links the Building Fee Schedule and Citywide Fee Schedule effective October 1, 2025, together with ADU submittal documents.

    Accessed August 28, 2026

  • The current official schedule uses base costs at square-foot thresholds and incremental costs per additional 100 square feet for plan check and inspection columns; the table has no dedicated ADU row.

    Accessed August 28, 2026