  1. 1

    Confirm pre-approved-plan and site-specific requirements

    For City pre-approved plan, contract with its designer Contact Planning and Permit Center about site-specific plans, studies and engineering For Master Plan, email application for staff-created ACA record Applicable pre-approved-plan/online record path

  2. 2

    Create ACA account and submit ADU/JADU application and documents

    Create ACA account Select Building/Create Application and complete online form Upload City-required plans/documents ACA record with Applied status

  3. 3

    Permit Center determines application completeness

    Provide City-requested missing information/actions Complete application for review or email describing missing items

  4. 4

    City conducts ADU/JADU ministerial review

    For standard single-family application, provide materials for Planning/Engineering review For multifamily application, follow City Community Development review route Approval, denial, or correction notice

  5. 5

    Respond to City comments and electronically resubmit

    Correct plans/documents Follow City responding-to-comments/resubmittal instructions Pay plan-check fee at resubmittal Resubmittal for further review

  6. 6

    Pay approval fees and receive permit/inspection-card documents

    Pay City-notified fees online Receive permit and inspection-card documents by email Access approved plan/documents in ACA Digital Projects and keep documents on site Issued permit, inspection card, and approved documents

  7. 7

    Request Building inspection by City form or phone

    Submit online Building Inspection request or call before City cutoff Provide permit number, address, onsite contact, inspection type and AM/PM preference Building inspection request/outcome

What you need to submit

  • Construction drawings including site plan
  • Existing-home elevations and photos
  • Title 24 energy calculations
  • General Construction Permit Application
  • JADU deed restriction

Pre-approved ADU plans

Use Livermore’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.

View pre-approved plans

Project-specific next step

Build your Livermore permit report

Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.

Start my permit report

Sources for this guide

Additional city reference pages

  • The City Permit Center page identifies the Master Fee Schedule, development-fee sheet, and separate construction-related schedules as its official fee sources.

    Accessed August 28, 2026

  • The current City schedule states that its fees are in effect July 1, 2026 and provides the area-, occupancy-, and construction-type-based new-construction fee table plus miscellaneous permit and review fees.

    Accessed August 28, 2026

  • The current City fee sheet supplies the ADU/JADU impact-fee rule, connection layers, school-fee collection condition, and current development-fee attachments.

    Accessed August 28, 2026

  • The City’s live pre-approved ADU page sets a $1,000 City flat plan-review fee, while retaining separately variable construction and inspection charges.