ADU permit process in Long Beach, California
Last verified August 28, 2026
Guide verified Prepared by GetYourPermit editorial teamReport an error
Long Beach's Development Services Department (Building & Safety and Planning Bureaus) reviews ADU permits, applying state ADU law directly since the city has not yet adopted its own local ADU ordinance. Unlike many nearby cities, Long Beach does not currently accept online ADU submittals - all construction documents and applications must be submitted in person at the Permit Center, with plan check fees due the same day. State law still requires the city to act on a complete application within 60 days.
Typical timeline
State law requires city action on a complete ADU application within 60 days; Pre-Approved ADU (PAADU) plans may be approved over-the-counter with same-day permit issuance.
Where to apply
- Office
- 411 W. Ocean Blvd., 2nd Floor, Long Beach, CA 90802
Step by step
- 1
Review planning requirements
Review the Planning Bureau's ADU Information Bulletin; check whether the property is in a Historic District (requires a Certificate of Appropriateness) or the Coastal Zone (requires a Local Coastal Development Permit before the building permit).
- 2
Prepare plans
Prepare a complete set of construction documents, saved as a digital PDF, either as a custom design or using a Pre-Approved ADU (PAADU) plan.
- 3
Submit in person at the Permit Center
Schedule an appointment or visit the Permit Center during business hours to submit the permit application and plans on a USB drive; plan check fees are due at submission.
- 4
Plan check and corrections
Planning and Engineering/Building staff review concurrently; resubmit revised plans as requested and monitor progress on the Plan Check Status webpage.
- 5
Pay permit fees and pick up documents
Once plans are ready-to-issue, you'll receive an email; pay remaining permit fees and obtain approved documents in person.
- 6
Construction and inspections
Schedule inspections online at each phase of construction.
- 7
Final inspection
Pass final inspection before occupying or renting the ADU.
What you need to submit
- Building permit application
- Complete construction document set (PDF on USB drive)
- Certificate of Appropriateness (Historic District properties only)
- Local Coastal Development Permit (Coastal Zone properties only)
Long Beach ADU rules at a glance
- JADU
- JADU capped at 500 sq ft; requires an efficiency kitchen and bathroom; may connect internally to the primary home; owner-occupancy required only if the JADU shares a bathroom with the main house.
- Height
- Reported as up to 16 ft in most zones, up to 18 ft (plus 2 ft for roof pitch) within 1/2 mile of a major transit stop. (Secondary source; not independently confirmed on an official page.)
- Parking
- One parking space generally required per ADU, waived within 1/2 mile of transit, for conversions, and per other state exemptions (e.g., near Metro A Line stops or Long Beach Transit BRT routes).
- Max size
- Detached ADU generally up to 1,200 sq ft; attached ADU generally up to 50% of existing living area (up to 1,200 sq ft); JADU up to 500 sq ft. (Figures from secondary sources summarizing state/local standards - not confirmed on an official numeric table.)
- Setbacks
- Reported 4 ft minimum side/rear setback for new-construction ADUs; reduced/no setback often applies to conversions of existing structures. (Secondary source.)
Pre-approved ADU plans
Long Beach publishes pre-approved plan sets, which can shorten plan check.
View pre-approved plansPractical tips
- Online submission is not available - bring your application and a PDF plan set on a USB drive to the Permit Center in person.
- Use a Pre-Approved ADU (PAADU) plan for potential same-day over-the-counter permit issuance.
- Check the SB 9 Parking Exemption Area map before assuming you need to provide a parking space.
- Confirm Historic District or Coastal Zone status early - both require an extra approval before the building permit can be issued.
Sources for this guide
Additional city reference pages
Secondary summary with ADU fee ranges and California ADU fee rule notes; useful for directional estimates but should be verified against official schedules.
Accessed May 31, 2026
Official city ADU page for local planning/building contacts and general ADU guidance.
Accessed May 31, 2026
Official city fee schedule page; confirms surcharge percentages and $90 processing fee.
Accessed May 31, 2026