This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.
Where to apply
- Department
- Building Division
- Permit portal
- City Online Portal System
Step by step
- 1
Review Town ADU/JADU requirements and application guidance
Review Town ADU reference and application packet Prepare a compliant plan and document package Single ADU/JADU application package
- 2
Upload complete ADU/JADU application package
Upload application, plan set and supporting PDFs through Citizen's Portal pre-application Use the Town's electronic document formatting requirements Town Building pre-application submission
- 3
Town confirms minimum submission and provides number/fees
Pay Town-provided required fees Building Permit application number and fee information
- 4
Town and conditional external-agency review
Respond to reviewers as needed Review comments or approval-ready package
- 5
Resolve reviewer corrections and upload resubmittals
Correct requested documents Upload new cycle plan and supporting-document files Resubmitted application package
- 6
Receive Building Permit after completed review
Complete outstanding conditions, if any, before Building Permit issuance Issued ADU/JADU Building Permit
- 7
Schedule construction inspections
Use online permits system, phone or fax route to request inspection Provide permit number, address and inspection type Scheduled inspection and confirmation
- 8
Complete final inspection and occupancy condition
Complete final inspection before occupancy Eligibility for occupancy
What you need to submit
- Completed ADU/JADU Building Permit application
- Complete PDF plans and supporting documents
- Recorded JADU deed restriction
Pre-approved ADU plans
Use Los Gatos’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.
View pre-approved plansProject-specific next step
Build your Los Gatos permit report
Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.
Sources for this guide
Additional city reference pages
The Town's live permit-fee page exposes the FY 2026-2027 building valuation table, $68 issuance fee, 65% plan review, and separate state-surcharge rules.
Accessed August 28, 2026
The official Council item recommends adopting the 2026-27 schedule and states approved changes become effective July 1, 2026.
Accessed August 28, 2026
The 2026-27 Town ADU packet requires an ADU/JADU construction valuation, routes the application through the portal, and states fee information is supplied once the application is complete.