ADU permit process in Napa, California

Last verified August 29, 2026

Prepared by GetYourPermit editorial teamReport an error

This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.

Where to apply

Step by step

  1. 1

    Confirm City eligibility and special conditions

    Use City-linked ADU resources Discuss height, historic, flood/fault, utilities and other site conditions with Planning/Building Building-only or conditional Planning-plus-Building route

  2. 2

    Complete conditional Planning approval

    Submit the applicable Planning/Administrative Permit materials Applicable Planning approval or conditions

  3. 3

    Submit paper Building Permit package and plan-review fee

    Bring the completed application and required paper plan sets/supporting documents to Building Pay the plan-review fee Full Review intake

  4. 4

    Concurrent City plan review

    Wait for Building and applicable departmental review Approvals or coordinated comments

  5. 5

    Respond to comments and resubmit

    Address all comments Submit revised plan sets and required resubmittal materials Secondary review

  6. 6

    Obtain sewer and applicable outside clearances

    Obtain the Napa Sanitation sewer permit Complete applicable water, utility, Environmental Health, school or other clearances Required permits and clearances

  7. 7

    Complete approvals and pre-issuance documents

    Resolve City comments Provide Napa Sanitation verification Complete JADU deed restriction when applicable Obtain remaining clearances Permit ready for fees and issuance

  8. 8

    Pay remaining fees and collect the Building Permit

    Pay remaining fees Collect the issued permit, job card and approved plan set Issued Building Permit, job card and approved plans

  9. 9

    Construct under the issued permit

    Post the issued documents on site Build to approved plans Submit a formal revision before deviating from issued plans Work ready for phased inspections

  10. 10

    Schedule and pass phased inspections

    Schedule by eTRAKiT, automated phone or Permit Technician Keep approved plans and job card on site Do not conceal work before approval Pay an assessed reinspection fee before the next inspection when applicable Signed inspection progress or corrections

  11. 11

    Complete final inspection and Golden Rod clearances

    Complete construction and final paperwork Pass Building final Obtain documented Planning, Fire, Public Works and applicable outside-agency approvals Final approval before use/occupancy

  12. 12

    Receive occupancy/permit close-out authorization

    Do not occupy until final approval and applicable Certificate of Occupancy are complete Applicable Certificate of Occupancy and permit close-out

What you need to submit

  • Residential Building Permit Application
  • Paper ADU plan set and supporting documents
  • Recorded JADU deed restriction — only in some cases
  • Napa Sanitation sewer permit verification
  • Golden Rod final sign-off sheet — only in some cases

Pre-approved ADU plans

Use Napa’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.

View pre-approved plans

Project-specific next step

Build your Napa permit report

Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.

Start my permit report

Sources for this guide

Additional city reference pages

  • The current City-hosted Master Fee Schedule gives an ADU/JADU-specific Building Permit fee and states that this Building fee includes plan review, inspection, fire plan check, and planning plan check.

    Accessed August 28, 2026

  • The live City ADU page confirms that ADUs proceed through an ADU permit application and that pre-reviewed plans still receive City compliance review before Building Permit issuance.

    Accessed August 28, 2026