ADU permit process in Pleasant Hill, California

Last verified August 29, 2026

Prepared by GetYourPermit editorial teamReport an error

This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.

Where to apply

Step by step

  1. 1

    Identify ADU class, site constraints and permit route

    Review City ADU page, 2026 handout and code Select custom or City pre-approved plan route Confirm project-specific planning, site and agency conditions Proposed permit route and document scope

  2. 2

    Submit City permit application and complete electronic plan package

    Create/sign in to PHill Submit permit application Upload application, plans and applicable supporting files City application received for completeness and review

  3. 3

    City determines ADU/JADU application completeness

    Provide itemized missing information when City issues an incomplete notice Written complete determination or itemized incomplete notice

  4. 4

    Pay initial plan-review invoice when technical review applies

    Pay the invoiced 50 percent permit fee through PHill Payment verified and case moved into plan review

  5. 5

    City performs ministerial and multidisciplinary plan review

    Monitor case status and respond to City requirements Discipline approvals or correction comments

  6. 6

    Receive emailed correction notice

    Review City correction comments Revise application, plans and applicable supporting material Revised complete-file resubmittal package

  7. 7

    Upload complete revised files through PHill

    Upload complete replacement APP/PLANS/SUPP files rather than changed sheets only Use the City cycle/file naming convention Revised package returned to City review

  8. 8

    Obtain applicable outside-agency and utility clearances

    Coordinate with applicable fire protection, sanitary and water authorities Upload or present required approvals Applicable agency permits or clearances

  9. 9

    Resolve outstanding items and pay final permit fees

    Satisfy outstanding City items Pay final fees through PHill Issuance payment and outstanding items completed

  10. 10

    Receive permit and approved Job Site Copy

    Download or receive approved documents Print and keep the Job Site Copy at the project site Issued permit and approved Job Site Copy

  11. 11

    Request available inspections through PHill

    Use the permit inspection tab after the workflow reaches inspection Select an available inspection action, requested date and AM/PM window Submitted inspection request and inspection records/status

  12. 12

    Satisfy final occupancy conditions when applicable

    For a JADU, record the required deed restriction before Certificate of Occupancy Complete final requirements identified by City Certificate of Occupancy when applicable; general administrative close marker not published

What you need to submit

  • Electronic APP, PLANS and applicable SUPP PDF package
  • Selected City pre-approved plan set, signed license and project/style information — only in some cases
  • Residential Building Permit & Zoning Application
  • Scaled property-specific site or plot plan
  • Applicable outside-agency permit or clearance documentation — only in some cases
  • Recorded JADU deed restriction — only in some cases

Pre-approved ADU plans

Use Pleasant Hill’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.

View pre-approved plans

Project-specific next step

Build your Pleasant Hill permit report

Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.

Start my permit report

Sources for this guide

Additional city reference pages

  • The live City ADU page says pre-approved plans still require a Building Permit and outside-agency clearance, and identifies outside fire, sanitary, and water providers.

    Accessed August 28, 2026

  • The City handout states all new ADUs and JADUs require Building Permit approval and some require a separate ADU Permit based on size or location.

    Accessed August 28, 2026