ADU permit process in Redwood City, California
Last verified August 29, 2026
Prepared by GetYourPermit editorial teamReport an error
This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.
Where to apply
- Department
- Building Division
- Permit portal
- City Online Portal System
- Contact
- (650) 780-7350
Step by step
- 1
Prepare City checklist and submit ADU Building Permit application
Complete City ADU checklist and plan package Set up eTrakIt account and submit Building Permit materials online For new detached ADU, request Fire Flow test Online Building Permit application
- 2
City planning/building review of project-specific plans
Respond through current City-directed review process if requested For a pre-reviewed design, complete customized site planning and permit application City review path
- 3
Complete City finalization item and receive Building Permit
Complete City ADU Homeowner Survey and submit confirmation as required Pay applicable City fees through eTrakIt Building Permit finalization/issuance path
- 4
Schedule Building inspections in eTrakIt
Use eTrakIt dashboard to schedule or cancel inspection Inspection scheduling
What you need to submit
- Digital PDF drawings and ADU plan set
- Fire Flow Report — only in some cases
- Structural and Title 24 energy calculations/forms
- ADU Homeowner Survey confirmation
Pre-approved ADU plans
Use Redwood City’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.
View pre-approved plansProject-specific next step
Build your Redwood City permit report
Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.
Sources for this guide
Additional city reference pages
The live City landing page links the Master Fee Schedule and labels it effective July 1, 2026.
Accessed August 28, 2026
The current City schedule lists ADU flat building-fee bands, a 50%-of-building-fee plan-check payment, and separately identifies utility capacity fees.
Accessed August 28, 2026