ADU permit process in San Mateo, California
Last verified August 29, 2026
Prepared by GetYourPermit editorial teamReport an error
This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.
Where to apply
- Department
- Building Division
- Permit portal
- City Online Portal System
Step by step
- 1
Create CSS account and submit complete ADU/JADU application
Create/confirm CSS account Upload complete plans, documents and project materials CSS pre-application that moves to full application after City processing
- 2
City Building, Planning and conditional agency review
Pay City-assessed application fees through CSS Receive comments and provide resubmittals through CSS For pre-approved plan, retain exact pre-approved design while adding site-specific materials Review comments or plans ready for issuance
- 3
Complete pre-issuance conditions and receive permit
Complete ADU affordability survey For JADU, record City-prepared deed restriction Pay other applicable conditions and fees as directed Permit issuance communication through CSS
- 4
Construction and inspection after issued permit
Proceed only after Building Permit issuance and follow City inspection requirements
What you need to submit
- Complete electronic Building Permit plan package
- Plot plan with site, utility and environmental information
- Pre-Approved Plan Phase 2 site-specific package
- Completed ADU Affordability Survey
- Recorded deed restriction
Pre-approved ADU plans
Use San Mateo’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.
View pre-approved plansProject-specific next step
Build your San Mateo permit report
Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.
Sources for this guide
Additional city reference pages
The City's current 2026-27 schedule lists four separately classified ADU/JADU flat permit fees.
Accessed August 28, 2026
The live ADU page states compliant ADUs/JADUs require a building permit and repeats current new-ADU, remodel-ADU, and JADU flat fees.
Accessed August 28, 2026