ADU permit process in Scotts Valley, California

Last verified August 29, 2026

Prepared by GetYourPermit editorial teamReport an error

This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.

Where to apply

Step by step

  1. 1

    Plan the ADU and confirm City/outside-authority requirements

    Review the City manual and property constraints. Meet City staff if needed. Identify applicable Fire, water, sewer or septic requirements. Applicable zoning, Building and service-authority constraints

  2. 2

    Prepare a custom or City-listed pre-reviewed design

    Select a custom or pre-reviewed path. Prepare construction drawings and property-specific materials. Review the initial design with City staff as needed. Permit-ready application materials

  3. 3

    Submit Building Permit application and plans in OpenGov

    Register in OpenGov. Upload the application, plans and applicable supporting materials. Pay initial applicable fees when requested. City Building Permit application record

  4. 4

    City Building plan check

    Monitor the OpenGov record for City comments and status. Wait for City plan-check comments or approval. Plan-check comments or permit approval

  5. 5

    Complete applicable Fire or utility requirements

    Coordinate with the applicable separate Fire/water/septic authority or City Public Works when the parcel/project triggers its requirements. Applicable authority requirements or approval

  6. 6

    Respond to comments and resubmit plans

    Address plan-check comments. Resubmit revised plans through the assigned City process. Corrected package for re-review

  7. 7

    Complete approval, outstanding fees and receive Building Permit

    Resolve required comments and applicable authority conditions. Pay outstanding fees. Receive the issued Building Permit before work. Issued Building Permit

  8. 8

    Select a contractor

    Request and compare bids. Select a qualified contractor. Selected contractor

  9. 9

    Construct under the issued permit

    Build according to approved plans. Monitor work and have the contractor request City inspections. Permitted construction ready for inspections

  10. 10

    Schedule and complete required City inspections

    Use OpenGov as applicant or added guest. Select the permit/application and request a New Appointment. Monitor confirmation and inspection results. Inspection appointment confirmation and results

  11. 11

    Pass final inspection before move-in or rental

    Complete construction and obtain City final inspection approval. Move in or rent only after the ADU passes final inspection. Passed final inspection and City-described readiness for move-in

What you need to submit

  • Building Permit application and construction plans
  • Legalization Building Permit application, site plan, as-built plans and substandard-condition corrections — only in some cases
  • Pre-reviewed-plan site-specific plan and supporting materials

Pre-approved ADU plans

Use Scotts Valley’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.

View pre-approved plans

Project-specific next step

Build your Scotts Valley permit report

Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.

Start my permit report

Sources for this guide

Additional city reference pages

  • The live City Building Department page links the Master Fee Schedule FY 26/27 and identifies OpenGov as the permit-application and fee-payment system.

    Accessed August 29, 2026

  • The City-hosted FY2026-27 Master Fee Schedule supplies current Building Permit and plan-check valuation scales and the named City and State surcharge formulas.

    Accessed August 29, 2026

  • The City-hosted impact-fee sheet is effective July 7, 2026 and expressly states that ADUs 750 square feet and under do not pay DIF; it provides current base schedules by zoning/use category.

    Accessed August 29, 2026

  • The City ADU Manual confirms that a compliant ADU needs a Building Permit without public hearing or discretionary review, gives the DIF and school-fee thresholds, and identifies utility and Fire District conditions.

    Accessed August 29, 2026