ADU permit process in Oakland, California
Last verified August 29, 2026
Prepared by GetYourPermit editorial teamReport an error
This guide includes the portions of the City permit process that passed our evidence review. Confirm project-specific requirements with the City before submitting.
Where to apply
- Department
- Building Bureau
- Permit portal
- City Online Portal System
Step by step
- 1
Prepare Zoning materials and submit Planning application
Confirm zone Prepare Zoning plan set/checklist Submit Planning materials through Online Permit Center Planning review intake
- 2
Obtain written Planning/Zoning approval
Respond to requests for missing or unclear information Written Planning approval
- 3
Submit Building application and plan package
Submit Building worksheet/application and required documents Pay applicable fees Building application created
- 4
City reviews plans and requests corrections or information
Respond to City correction/information contact Meet applicable utility requirements Final Zoning and Building approval path
- 5
Complete Final Check before permit issuance
Provide outstanding final documents and fees Permit-ready record
- 6
Receive and print issued permit, inspection card and plans
Print permit, inspection card and plans Keep documents on building site Issued permit and job documents
- 7
Schedule inspections, correct issues and complete final inspection
Schedule inspections by City app or call Correct failures before reinspection Submit recycling final report before final inspection Passed inspections and final approval
- 8
City processes Certificate of Occupancy after final inspection
Certificate of Occupancy mailed to owner address
What you need to submit
- Zoning/application materials: existing/proposed site plans, floor plan, elevations and cross sections
- Building plan requirements and Building Criteria Checklist
- Recycling final report / Green Halo summary report
Pre-approved ADU plans
Use Oakland’s official page to confirm which designs, site conditions, and supplemental documents qualify. Plan-check timing still depends on the project and city review.
View pre-approved plansProject-specific next step
Build your Oakland permit report
Choose your ADU type and size to bring the City process, researched permit fees, and early construction budget into one planning report.
Sources for this guide
Additional city reference pages
The current City page links the FY 2025-26 adopted master schedule, zoning schedule, and 2025 impact-fee sheet. It had not exposed an FY 2026-27 building schedule when accessed.
Accessed August 28, 2026
The adopted schedule, effective August 28, 2025, publishes separate R3 plan-review and inspection rates per $1,000 of construction valuation with stated minimum fees.
Accessed August 28, 2026